Title: Fairfield Art Centre

Sector: Public Sector
Date of completion: September 2018
Location: Fairfield
Project timeline (weeks): 10 weeks
Value: £170,000

Description of project:

Strip out existing boiler plant and hot water system, reinstallation of new boiler plant and BMS Control Systems. Installation of instantaneous water heaters.

Work completed:

  • BMS Control
  • LTHW Heating
  • Gas-fired Hot Water System
  • Natural Gas
  • Testing and Comissioning