Title: Moonfleet Manor

Sector: Leisure
Date of completion: Feburary 2017
Location: Weymouth
Project timeline (weeks): 4 weeks
Value: £88,000

Description of project:

Boutique, luxury family hotels. A particularly challenging project as it was essential that the hotel remained open throughout the project. We effectively installed temporary boilers and generators while we carried out the replacement.

Work completed:

  • Boiler plant replacement
  • Domestic hot water plant installation
  • Upgrading of BMS controls
  • Electrical installations

 