Title: University Hospitals Bristol – Heygrove AHU 5&6 Cooling Upgrade

Sector: Healthcare
Location: Heygrove Suite BRI
Project timeline (weeks): 2 weeks
Value: £45,000.00

Description of project:

This project was a replacement of the existing end of life cooling systems to 4no Supply air handling units within the theatre of the BRI. The works consisted of removal of the existing cooling condensing units and internal cooling coils for 4no systems and replacement with new updated equipment.

Due to the nature of the areas these were feeding a careful program of works and liaison with the estates staff and clinical staff was imperative. Minimal downtime for each system had to be ensured to reduce any potential disruption or delay to the operations that were planned. Out of hours works were undertaken which included a crane lift to position and remove the existing/new condensers.

Work completed:

  • Decommission of Existing F-Gas Refrigeration equipment
  • Site sizing and manufacture of new cooling coils
  • Electrical Installation
  • Refrigeration Installation
  • BMS Integration
  • Specialist Crane Lift