Title: Whitstone School
Sector: Education
Date of completion: September 2016
Location: Shepton Mallet
Project timeline (weeks): 6 weeks
Value: £180,000
Description of project:
Removal of existing plant and equipment, and design, supply and install new in 3 teaching blocks. Very tight immovable timeline, due to school term starting in September. Had to be completed over summer.
Work completed:
- Industrial boiler removal
- Installation of boiler plant and associated equipment
- Natural gas
- Hot and cold-water systems
- Testing and commissioning